tankopbouw

 


Fase 1: Building chassis juli/augustus 2013

Herman Persyn

chassischassis

 

 

 

 

 

 

 

 


Fase 2: Installing Chains and engine september 2013

vandaele

 

tank op kettingentank op kettingen

 

 

 

 

 

 

 


Fase 3: Design and Installation tracks November 2015-2016

steeno

 

track

3d track

 

 

 

 

 

 

 

 

trackstracks

 

 

 

 

 

 


Fase 4: Platework april-juni 2017

deswartelvd

 

 

beplatingbeplating

 

 

 

 

 

 


Fase 5: Finishing new Jcb engine maart 2018

briekmann

 

JCBmotorJCB motor

 

 

 

 

 

 

 

 

 

 

 

 


Fase 6: Changing Gardner engine with Jcb mei 2018

vervangenjcb


Fase 7: Platework roof + 1st primer juni-juli 2018

 

deswarteolifant

 

 

dakbeplatingbeplating

 

 

 

 

 

 

 

 

 

 

 

 


Fase 8: Painting top layer juli 2018

olifant
schilderen

Fase 9: Changing Hydropumps december 2018-januari 2019

vervaekehydrauvision

 

 

pompen

 


Fase 10: Fase 11: Finishing Male sponsons/ Sponsorplate juni 2019

pondfarm

sponsonsponsorplaat

 

 

 

 

 

 

 

Fase 11: Installing 3 Emergency stops/ Lights/usb connection/Camera/Remote Control

pondfarm

noodstop

Fase 12: installing shackles, spare wooden blocks september 2019

pondfarm

schackleswoodenblocks

 

 

 

 

 

 

 


Fase 13: Pressure controll cabine january 2020

pondfarm

noodstop

 


Phase 14: Rubber pads, octobre 2021

pondfarm
 
rubberpads
team junior
Team Junior

pondfarmPhase 15: Finishing roof/ cabine + exhaustpipe + unditching beam, detailwork, 2022

 

 

 

montage rail

Phase 16: Wireless RC, 2022-2023


Phase 17: New jcb hydro-engines 2023-2024


end result

End Result